We’re thrilled to share some exciting updates on our ongoing construction project. Here are the key highlights and developments:

Project Milestones:

Foundations are now complete.
Site Utilities are continuing with the storm water piping. The storm pond is complete.
Masonry has started around the perimeter of the building as well as the high wall masonry on the gymnasium walls.
Technology is now under contract.
Furniture – the team is setting up discovery meetings to start designing the furniture layouts for the building.
Overall project remains on track and hoping to build upon the momentum.